Project Milestone Schedule of the Project in Part I 2003-01-13 1. Preliminary specifications: sent to potential and interested suppliers before study tour 2. Study Tour: July-Aug. 2003 3. Finalize specifications and other bid terms and conditions: Aug. 2003 4. Release request for proposals: Fall of 2003 5. Receive and evaluate bid documents: 3 months after releasing request for proposals. 6. Signing contract with suppliers: March, 2004 7. Installation of hydrogen supply system: about 5 months after signing the contracts 8. Delivery of the first 6 fuel cell buses: 6 months after signing the contracts Notice: Some activity above may be delayed due to SARS. |